Hand-offs

The Hand-offs page displays the full network of tasks and task milestones in your project. The page is optimized for creating and modifying task hand-offs in a variety of ways. You can also add tasks, assign constraints, create hand-offs between tasks, and commit to perform the task work.

By default, this page displays a planning period of six weeks (one week before the current week, the current week, and four weeks after the current week). Tasks outside the planning period may not be visible. To modify the current settings, see Configure and Apply Filtering.