Time phased data for scope assignments, by default, is evenly spread according to the specified dates assigned to scope assignments. You can redistribute original hours and quantities for scope assignments per timescale interval using curve profiles or by manual distribution using the Time Phase view. This process occurs before the original baseline is set.