Manually Distribute Hours and Quantities Per Timescale Interval for a Scope Assignment

Original hours and quantities can be manually updated per timescale interval.

Note: Once you make a manual update to original hours or original quantities using the Time Phase view, certain fields on the Plan view will no longer be editable for the scope assignment. These fields are Original Hours, Original Quantity, Original Productivity Rate, Original Cost, Original Cost Rate, and Rate By.

To manually update original hours and quantities per timescale interval:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Scope, and then select Scope Assignments.
  3. On the Scope Assignments page, in the Work Package field, select the name of the work package.
  4. Select Time Phase.
  5. To change the timescale interval:
    1. Select Settings.
    2. In the Setting dialog box, select the Timescale tab.
    3. In the Timescale Interval field, select the timescale to use for planning.
    4. Select Apply.

      Note: You can also change the timescale interval by right clicking on the timescale in the table and selecting an option.

  6. Update the individual timescale intervals for Original Quantity or Original Hours as necessary. Updating these fields will automatically adjust the Original Cost field.

Tips