Assign an Activity to a WBS

All activities must be assigned to a WBS. Assign activities to a WBS to group work by level, phase, or layer. In scope management, you cannot assign activities to work packages or scope assignments unless the activity is assigned to the WBS that contains the component. If a specific WBS node is not selected when an activity is created, the activity is assigned to the project-level WBS node by default.

To assign an activity to a WBS:

  1. Navigate to the Activities page
  2. In the table, select the activity.
  3. On the Layout menu, select Activity Details, and then select the General detail window.
  4. In the WBS Name field, select a WBS.
  5. All changes made to this page are saved automatically.