Specify Calendar Availability for Assignment
Before calendars can be assigned, they must be made available to supporting objects. Each workspace-level calendar can be made available to projects, resources/roles, or both. Both options as selected by default when a calendar is created. If a calendar is not available to one of these objects, it will not appear as an option when assigning calendars to that type of object.
The calendar set as the default calendar is automatically made available to projects, resources, and roles. This can only be changed if you set a different calendar as the default.
To specify calendar availability:
- Navigate to the Calendars dictionary page
- In the object selector, select Workspace, select View Workspaces List, and then select a workspace name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Dictionaries, and then select Calendars.
- Select a calendar.
- Select the Summary tab.
- In the Available To section, select Project, Resource/Role, or both.
- Select Save.