Add a Task or Task Milestone to a Pull Plan on the Planning Board

Add a task to represent work in a pull plan. Add a task milestone to mark a significant point in the planned sequence. For example, a concrete foreman can add a task for placing reinforcing steel and a task milestone for completing the slab pour.

A pull plan can contain a maximum of 5,000 tasks and task milestones across the Planning Board and Parking Lot.

Note You can add tasks and task milestones only to an In Planning pull plan.

To add a task or task milestone to a pull plan on the Planning Board:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Tasks, and then select Pull Plans.
  3. Select an In Planning pull plan to open its Planning Board.
  4. Add a task or task milestone using one of the following methods:
    1. On the toolbar:
      1. On the Planning Board toolbar, select +.
      2. Select Task or Task Milestone to open the Add Task panel.
      3. In the Add Task panel, complete the following fields, as applicable:
        • Task Name or Task Milestone Name: The name of the task or task milestone. You can add up to 255 characters.
        • Company: The company responsible for performing the task. If you have only the Add task for My company privilege, the Company field is disabled; otherwise, the Company field defaults to your company.
        • Duration: The planned number of days required to complete the task. This field defaults to 1 day.
        • Crew Size: The number of workers needed to complete the task. This field is blank by default.
        • What I Need: Information about the materials, resources, or conditions needed to begin the task. You can add up to 255 characters.
      1. Code: A task code value used to classify the task. This field retains the value selected most recently during the current sign-in session. Note This field is available only when the project uses a task code for color coding.
  5. Select Add.
  6. Select Add and Add Another to create additional tasks.
  7. On an empty area of the Planning Board:
    1. Double-click or right-click an empty area of the board and select Add Task. To add a task milestone, double-click or right-click an empty area in the milestone area at the top of the board and select Add Task Milestone.
    2. Enter a name and any other applicable details, then select Add. A task snaps to the selected column; a task milestone snaps to the selected column line. You cannot add an ordinary task from the milestone area.
  8. On an existing task or task milestone:
    1. Right-click the task or task milestone and select Add Task Before or Add Task After.
    2. Enter the task or task milestone details, then select Add.

Tip

Use Add Task Before or Add Task After when the new work must have a hand-off relationship with an existing task or task milestone. If a row is occupied, the new task is placed in the next available row below. A new task milestone is placed on the nearest eligible column line on the selected side. Both actions create the applicable hand-off.