Dissolve an Activity

Dissolving an activity enables you to delete the activity from your project schedule while maintaining the activity's predecessor and successor relationships.

When you dissolve an activity, the following changes occur:

For example: Activity A forms a Finish to Start relationship with Activity B, with 1 day of lag. Activity B forms a Finish to Finish relationship with Activity C, with 2 days of lag. If Activity B is dissolved, then Activity A will form a Finish to Finish relationship with Activity C, with 3 days of lag.

To dissolve an activity:

  1. Navigate to the Activities page
  2. Select an activity, select the Context menu, and then select Dissolve.
  3. All changes made to this page are saved automatically.

Tips