Assign a Curve to a Resource or a Role Assignment
A curve profile can be selected per activity assignment to allocate resource or role units over the duration of an activity according to a specific curve. Units spread are Planned Units, Actual Units, Remaining Units, and At Completion Units.
Note: Curves may cause an assignment's costs to be recalculated if the assignment's Calculate Costs from Units setting is enabled.
A curve profile can be assigned to any resource or role assignment on activities with one of the following duration types:
- Fixed Duration & Units/Time
- Fixed Duration & Units
To specify a curve profile:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- In the table, select the activity.
- On the Layout menu, select Activity Details, and then select the Resource Assignments detail window.
- In the Curve column for the resource assignment, select a curve.
- All changes made to this page are saved automatically.