Configure Schedule Settings for a Project

Configure project schedule settings to set planned project start and finish dates, as well as a date by which the project must finish. These dates are also used to drive the project scheduler during the scheduling process.

To configure schedule settings for your project:

  1. Navigate to the project Details page
  2. In the Schedule section, in the Project Planned Start field, select the start date.
  3. In the Project Planned Finish field, select a planned finish date.
  4. In the Schedule Must Finish By Date field, select the date the project must finish by.
  5. Select Save.

This setting is used in the following apps:

Resources
Risk
Schedule
Scope
Tasks