Assign Work Availability and Rates to a Project Resource
The resources available to your project may have a variety of work availability periods and pay rates. This information is essential when deciding which resources should be assigned to the activities in your project based on availability and cost.
You can define multiple availability periods for an individual resource, each with up to five separate pay rates. For more information on availability and rates, see Understanding Resource Availability and Rates.
Notes:
- When new rates are added, recalculate the schedule and recalculate costs to ensure all cost values are current.
- If you frequently export and import data, either to Primavera Cloud or P6 EPPM, a resource or role's availability and rate values should be identical at the workspace and project levels. Resource and role values are imported at the workspace level only. If a project-level resource or role is created as part of the import, it will use the values that exist at the workspace level. Existing project-level availability and rate values will not be overwritten. If you want to update project-level availability and rate values, you should do so manually.
To assign work availability and rates to a project resource:
- Navigate to the project resources page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Resources, and then select Resource List.
- In the table, select the resource.
- Select the Availability & Rates detail window.
- Select Add.
- In the new row, complete the following fields:
- Effective Start Date: Select the date for the availability period to begin.
- Max Units/Time: Enter the resource's maximum work units per time for this availability period. Enter these values as units per duration or as a percentage. The value will automatically convert to your format preference. The default Units/Time value can be set in the General detail window.
- Price/Unit: Enter up to five different rates for the availability period.
Note: Select Settings in the page toolbar to modify the currency view settings.
- All changes made to this page are saved automatically.
Tips
- Unit and duration labels, as well as the format for Units/Time, are set in the user preferences.
- Currency display options are configured in the page view settings. Project resource rates may be displayed in either base or project currency, depending on the currency and the view settings for the page. If a project resource is promoted to the parent workspace, its rates will only be displayed in base currency.
- The Owned By column indicates the workspace or project to which the resource belongs. Most resource information can only be edited in the workspace or project where it is owned.
Last Published Wednesday, October 16, 2024