Link an Activity to a Scope Assignment

Video

Link activities to scope assignments when you want to manage scope assignment dates using activity dates. This enables you to more accurately manage the time phase distribution of scope data for scope assignments.

Only one activity can be linked per scope assignment.

To link an activity to a scope assignment:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Scope, and then select Scope Assignments.
  3. On the Scope Assignments page, in the Work Package field, select the name of the work package.
  4. Select Plan or Status.
  5. In the table, select the scope assignment.
  6. Select the Activities detail window, and select Link.
  7. In the Link Activity dialog box, select an activity and select Link.

    Note: Only activities that are assigned the same WBS as the scope assignment's work package are available. Activities that are assigned to other work packages and activities that are assigned to scope assignments in other work packages are filtered out.

  8. Select Save.