Set the Data Date for a Project
The data date is the progress point, or "as-of date," for activities in the project. Project status is up-to-date as of the data date.
The data date is also used for updating the dates of scope assignments and work packages when they are not linked to activities.
Note: Dates will not change after the Data Date is updated for activities or scope assignments unless you run the Scheduler or Modify Dates feature, respectively.
To set the project data date:
- Navigate to the project Details page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Details.
- In the Details section, in the Data Date field, select the date.
- Select Save.
This setting is used in the following apps:
Cost and Funds |
碌Dashboards |
Reports |
Resources |
Risk |
Schedule |
Scope |
Tasks |
Last Published Wednesday, October 16, 2024