My Activities Fields
The below fields shown on the My Activities page can be added by you from the page’s view settings or by your manager using the Summary and Settings My Activities tab. Some general fields that are generic across the application, such as name or status, may not be included in this list.
Fields added by you are available for use across all of your projects and activities while fields added by your manager vary by project.
User Menu: My Activities page
Fields listed below are configurable by you through the user menu on the My Activities page.
Dates
BL Finish
The current finish date for the activity in the baseline.
The following baselines have unique names and values for this field: Original and Current.
BL Start
The current start date for the activity in the baseline.
The following baselines have unique names and values for this field: Original and Current.
Finish
The current finish date for the activity.
Start
The current start date of the activity.
For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.
Durations
Total Float
The amount of time the activity can be delayed before delaying the project finish date. Calculated as Late Start minus Early Start or as Late Finish minus Early Finish.
Units
Planned Units
The planned units for the work scheduled to be completed by a specified project date.
Summary & Settings Project Settings: My Activities Tab
Fields listed below are configured by your manager on the My Activities tab in the project Summary & Settings. Up to three Assignment Fields and three Activity fields can be displayed per project.
Assignment Fields
These fields may be visible for activities that you are assigned as a resource:
Remaining Duration
The remaining working time for the assignment, from the current date to the scheduled assignment finish date.
Actual Units
The amount of work that you have performed on the assignment.
Remaining Units
The amount of work to be performed on the assignment.
Activity Fields
These fields describe information about the overall activity. These activity fields may be visible for activities that you are assigned as an activity owner:
Expected Finish
The date you expect work on the activity to finish.
Remaining Duration
The total working time from the activity remaining start date to the remaining finish date.
Actual Nonlabor Units
The number of nonlabor units that have been expended on the activity.
Remaining Nonlabor Units
The remaining units for all nonlabor resources assigned to the activity.
The remaining units reflect the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the planned units. After the activity is completed, there are zero remaining units.
Activity Percent Complete
The percentage of the activity that has been completed.
Remaining Labor Units
The remaining units for all labor resources assigned to the activity.
The Remaining Labor Units reflect the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the planned units. After the activity is completed, the remaining units are zero.
Actual Labor Units
The number of units expended for all labor resources assigned to the activity.
Last Published Wednesday, October 16, 2024