Assign Work Availability and Rates to a Workspace Role

The roles available to your workspace may have a variety of work availability periods and pay rates. This information is essential when deciding which roles should be assigned to the activities in your projects based on availability and cost. If you are using roles for high-level project planning before assigning specific resources, you can use role rates to estimate costs for different job types and skill levels. The specific resources you associate with each role may have more accurate availability and rate data.

You can define multiple availability periods for an individual role, each with up to five separate pay rates. For more information on availability and rates, see Understanding Role Availability and Rates.

Note: When new rates are added, recalculate the schedule and recalculate costs to ensure all cost values are current.

To assign work availability and rates to a workspace role:

  1. Navigate to the workspace role page
  2. In the table, select the role, and then select the Availability & Rates detail window.
  3. Select Add.
  4. In the new row, complete the following fields:
    • Effective Start Date: Select the date for the availability period to begin.
    • Max Units/Time: Enter the role's maximum work units per time for this availability period. Enter these values as units per duration or as a percentage. The value will automatically convert to your format preference. The Default Units/Time value can be set in the table.
    • Price/Unit: Enter up to five different rates for the availability period.

      Note: Select Settings in the page toolbar to modify the currency view settings.

  5. All changes made to this page are saved automatically.

Tips