Assign a Risk Matrix to a Project or Program

Video

Assign a risk matrix to a project or program to calculate risk scores for threat and opportunity risks added to the risk register. The assigned risk matrix copies its data from a risk matrix template at the workspace level. You can edit threshold values on the assigned matrix without affecting the values at the workspace level.

To assign a risk matrix to a project or program:

  1. In the object selector, select Project or Program, and then select a project or a program from the list.
  2. From the Main Menu, select Summary & Settings.
  3. On the Summary & Settings page, select Dictionaries, and then select Risk Matrix.
  4. On the Risk Matrix page, select Assign.
  5. In the Assign Risk Matrix dialog box, select a risk matrix, and select Select.
  6. In the Scoring Method list, select one of the following risk scoring methods:
    • Highest Impact: The overall impact for a risk is set to the highest of all the impacts assigned to the risk.
    • Average Impact: The overall impact is determined by calculating the average of all impact values.
  7. Select Save.

Tips

This setting is used in the following apps:

Risk