Set the Activity Percent Complete Weight Method for a Work Package
Setting the Activity Percent Complete Weight Method enables you to determine how Activity Percent Complete will be calculated for the activities assigned to the work package and scope assignments.
To set the activity percent complete weight method:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Work Packages.
- In the table, select the work package.
- Select the General detail window.
- Select the Activity Weight Method. The Activity Weight Method option is used to determine how the Weight field for an activity will be populated: manually, or automatically using the Duration, Labor Units, or Non Labor Units for the activity.
Using the appropriate value as specified for the work package, the Activity Percent Complete for the work package is calculated as the sum of Completed Weight divided by the sum of Weight for all activities assigned to the work package and scope assignments. Completed Weight equals Weight multiplied by Activity Percent Complete for each activity.
- Select Save.
Last Published Wednesday, October 16, 2024