Add a Work Package Transfer to a Change Request
Add work package transfers to transfer assigned quantities from one scope assignment in a work package to one or more work packages.
To transfer scope assignment quantities:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Work Package Changes.
- In the table, select the ID for the work package change request.
- On the Work Package Changes details page, select the Transfer Scope Assignments tab.
- Select Add.
- In the Add Transfer dialog box:
- In the Source Work Package field, select the work package where the scope assignment is currently assigned.
- In the Source Scope Assignments section, use the search to locate the scope assignment. Select one or more items (Ctrl + click) and select Select.
- In the Source row, complete the following field:
- Transfer Quantity: Enter the quantity to be distributed to one or more work packages.
- In the Destination row, complete the following fields:
- Work Package: Select Select. In the Select Work Package dialog box, select the work package the scope assignment is to be transferred to.
- Type: Select the type of transfer to be made on the scope assignment.
- New: To add a new scope assignment for the destination.
- Update: To update an existing scope assignment for the destination.
- Scope Assignment: If the Type is Update, select the field and select Select. In the Select Scope Assignment dialog box, select the scope assignment to add additional quantities to.
- Scope Assignment ID: If the Type is New, the ID is generated automatically based on project settings. Adjust as needed.
- Transfer Quantity: Enter the quantity to be distributed to a work package.
- Transfer Cost Rate or Transfer Cost: Enter the cost rate or cost. The field that was not populated will be calculated accordingly based off the Rate By setting.
- (Optional) Transfer Start: Select the date the transfer will begin.
- (Optional) Transfer Finish: Select the date the transfer will end.
- (Optional) Cost Impact: Select to indicate there is a cost impact.
- (Optional) Schedule Impact: Select to indicate there is a schedule impact.
- (Optional) Description: Enter information about the transfer request.
- If there are remaining quantities to distribute, select the Context menu and select Add Destination.
- Continue to distribute remaining quantities.
- Select Save.
Note: The Productivity Rate, Rate, and Rate By values of the new scope assignment in the new work package are inherited from the source assignment; however, these values can be updated as needed.
Last Published Wednesday, October 16, 2024