Assign a Manager to a WBS
Assign managers to WBS elements to identify the project manager or person responsible for managing the WBS.
The person who created the project is automatically assigned as the manager. The person who is assigned to a parent WBS node is automatically assigned as the manager to child WBS nodes.
The functionality described in this topic applies to the following pages in the application:
- Activities
- WBS
To assign a manager to a WBS:
- Navigate to the main table on a page.
- In the table, select a WBS, and then select the General detail window.
- In the Manager field, select a manager.
- All changes made to this page are saved automatically.
Last Published Wednesday, October 16, 2024