Add a Work Package
A work package without scope items or activities assigned to it may also be referred to as a planning package. As soon as a scope item is assigned, the planning package becomes a work package.
Note: After a baseline is set, each new work package must be added by submitting a change request.
To add a work package:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Work Packages.
- Select Add.
- In the new row, complete the following fields:
- Name: Enter a name for the work package.
- ID: The ID is generated automatically based on project settings. Adjust as needed.
- WBS: Select the WBS to associate with this work package. If the project does not use a WBS, then associate the work package with the default WBS.
- Original Start: Select the date the work on the work package is scheduled to begin.
- Original Finish: Select the date the work on the work package is scheduled to finish.
- Select Save.