View Risk Analysis Distribution Results

The distribution graph displays Remaining Cost, At-Completion Cost, Duration, Start Date, and Finish Date probabilities, as well as the Schedule & Cost Scatter Plot, for the entire project and individual activities.

To view risk analysis distribution results:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Risk, and then select Risk Analysis.
  3. Select the Distribution Results tab.
  4. In the View field, select the project or an individual activity to view results data.

    Note: Available activity results are determined by your risk analysis settings.

  5. If enabled, in the Response Context list, select an analysis context:
    • Pre-Response: Displays analysis results based on pre-response values.
    • Post-Response: Displays analysis results based on post-response values.
    • Pre- and Post-Response: Displays analysis results of both response contexts.

      Note: When viewing the Pre- and Post-Response context, the pre-response is displayed in front of post-response. Post-response bars may be hidden completely if the pre-response value is greater than the post-response value.

  6. Use the tabs on the page to view Remaining Cost, At-Completion Cost, Duration, Start Date, Finish Date, and Schedule & Cost distributions. You can also view statistics and analysis settings on each tab.

Tips