Configure Gantt Curtains on the Activities Page
Gantt curtains can be customized using various colors, opacity options, and sizes, depending on the needs of your project team. Preview your changes before applying them to the schedule.
Create multiple curtain styles and manage them as needed from the Manage Views panel, or directly from the Activities grid when in Gantt view. See Gantt Curtains Overview for more information.
To enable and configure Gantt curtains from the Manage Views panel:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- Select Activities Grid Settings.
- In the Manage Views panel, select the Gantt tab, and then select the General tab.
- In the Show section, select Curtains to display curtains in Gantt view.
- At the top of the panel, select the Curtains tab to configure curtain settings.
- Select Add to create a new curtain, and then customize it using the following options in the grid:
- Name: Add a name for the Gantt curtain.
- Description: Add a significant description for your project team. This description displays with the Name and Start and Finish dates when a user hovers over the curtain name.
- Start: Enter the starting point for the curtain to display.
- Finish: Enter a finishing point for the curtain to close.
The default length of the curtain relates to the selected timescale. For example, if the timescale is set to Week/Day, then the default length is 1 week.
- Color: Apply a color to the curtain. The default selection is mint green.
- Opacity: Select an opacity level for your curtain. The range is 0 to 100%, with 100% being the default value.
- Visibility: Select this option to show or hide the curtain in Gantt view. When you create a new curtain, this option is selected by default.
- Apply the view:
In the Manage Views panel:
- Select Save. When selected, you are saving all changes to the current view.
- Select Save As. When selected, you can create a new Personal, Project, or Workspace view with a new name in the Save View as window.
- Select Apply. When selected, you are returned to the grid. The grid displays any changes you have made; however, those changes are not saved. To save changes select Save or Save As in the View list.
- Select Reset.
- Select Close.
In the Settings panel:
- Select Save.
Tips
- You can delete one or more curtains from the Curtains menu in the Gantt tab. Select one or more curtain rows, and then select Delete from the Context menu beside the curtain name.
Last Published Wednesday, February 19, 2025