Assign a WBS to a Task or Modify a WBS on the Task List Page
If there are tasks in your project that are not associated with an activity, you can assign a WBS to the task or edit one directly from the Task List page.
To assign a WBS to a task on the Task List page:
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Tasks, and then select Task List.
- In the table, select the task.
- In the WBS column, select a WBS.
- All changes made to this page are saved automatically.
Note: Assigning tasks to WBS nodes with no activity assignment is usually only a temporary state that can assist with pull planning. Those tasks will not appear on the Activities page until they are assigned to an activity.
Tips:
- You can also assign a WBS to a task using the Task Cards tab on the Work Plan page or on the Hands-offs page. See Customize Task Cards.
Last Published Wednesday, October 16, 2024