View the Activity Usage Histogram

View the activity usage histogram for a time-phased view of your activity usage. The data in the activity usage histogram is an aggregated total of all activities.

To view the activity usage histogram:

  1. Navigate to the project Activities page
  2. On the Activities page, in the Open menu, select Current Schedule.
  3. Select the Layout menu, and then select Project Usage.
  4. In the detail window, select the Activity Usage tab.
  5. Before viewing your activity usage data, configure the usage settings to ensure the appropriate information is displayed, such as units or costs, bars, curves, and legend details.
  6. In the histogram, hover over a bar or a plot point on a curve to view its details.

Tips