Deliver a Constraint
After a constraint has been resolved, you can deliver the constraint. The delivered date of the constraint is automatically set to the current date, but you can modify this from the Delivered Date column. The Status of the constraint is updated to Delivered.
To deliver a constraint:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Tasks, and then select Constraints.
- On the Constraints page, select a constraint row, select the Context menu, and then select Deliver.
- All changes made to this page are saved automatically.
Tips
- Clear the Delivered Date column to remove the delivery of the constraint and return the status to Not Planned (if no Promised Date is set) or Planned (if a Promised Date is set).
- To deliver multiple constraints at one time, use Ctrl + click to select multiple constraints, select the Context menu, and then select Deliver.
- You can also deliver a constraint by entering a date in the Delivered Date column.