Deliver a Constraint

After a constraint has been resolved, you can deliver the constraint. The delivered date of the constraint is automatically set to the current date, but you can modify this from the Delivered Date column. The Status of the constraint is updated to Delivered.

To deliver a constraint:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Tasks, and then select Constraints.
  3. On the Constraints page, select a constraint row, select the Context menu, and then select Deliver.
  4. All changes made to this page are saved automatically.