Specify Project-level Calendar Availability for Assignment

Before calendars can be assigned, they must be made available to supporting objects. Each project-level calendar can be made available for assignment to the project or to project resources and roles.

Making project-level calendars available to the project enables you to set it as the default project calendar or to individual activities in the project. The option is selected by default when a calendar is created.

To specify project-level calendar availability:

  1. Navigate to the project Calendars dictionary page
  2. Select a calendar.
  3. Select the Summary tab.
  4. In the Available To section, select Project, Resource/Role, or both.
  5. Select Save.

Tips

This setting is used in the following apps:

Cost and Funds
Resources
Risk
Schedule
Scope
Tasks