Promote a Project-level Calendar to the Parent Workspace
If a project-level calendar should be made available to other projects in the workspace, you can promote it to the parent workspace. If the promoted calendar's ID is not unique throughout the parent workspace's hierarchy, the promotion will fail. If this occurs, modify the ID and try again. After the calendar is promoted, it is removed from the project-level Calendars dictionary.
You must have the required security privileges to add a calendar in the parent workspace.
To promote a project-level calendar to the workspace:
- Navigate to the project Calendars dictionary page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Dictionaries, and then select Calendars.
- In the calendar list, select a calendar, select the Context menu, and then select Promote to Workspace.
- All changes made to this page are saved automatically.
This setting is used in the following apps:
Cost and Funds |
Resources |
Risk |
Schedule |
Scope |
Tasks |
Last Published Wednesday, October 16, 2024