Assign a Task to a Constraint on the Constraints Page
Identify the tasks that will be impacted by each constraint on the Constraints page. Identified tasks display in the Impacted Tasks column on the Constraints page within the grid. If a task can't begin before a constraint is resolved, then it should be associated with that constraint. You can assign multiple tasks to a single constraint, and the same task can be assigned to multiple constraints. Task data on the Constraints page is read-only.
To assign a task to a constraint on the Constraints page:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Tasks, and then select Constraints.
- In the table, select a constraint, and then select the Impacted Tasks detail window.
- In the detail window, select Assign, and then select one or more tasks to associate with the current task constraint.
- Select Select.
- All changes made to this page are saved automatically.
Tips
- In the Impacted Tasks detail window, select one or more tasks, and then select the Context menu to assign a new task to the current constraint or remove the selected tasks from the constraint.
- Select a task name from the Impacted Tasks detail window to view the task on the Task List page.
- You cannot assign a private task to a constraint.