Propose and Accept a Task Due Date on the Work Plan Page
When a task is part of a hand-off chain, directly modifying its due date may affect the due dates of other tasks in the chain. If the hand-off chain contains tasks from different companies, each company should be aware of the potential changes to their tasks. To solve this issue, updated due dates can be proposed without affecting the actual task due date. This enables the companies with tasks in the chain to review proposed due dates before they are accepted.
When a proposed due date is accepted, it is removed from the task and becomes the current task due date. If the accepted due date occurs on a non-work day, the Use Only Work Days setting is cleared and the due date is updated. If a task with a proposed due date is committed, the proposed due date is removed, and the current due date is updated to match the committed due date.
To learn more about task due dates, see Understanding Tasks App Concepts.
To propose and accept a task due date on the Work Plan page:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Tasks, and then select Work Plan.
- On the Work Plan page, right-click a task in the hopper or planning board, and then select View Task Details.
- In the Task Details dialog box, in the Proposed Due Date field, select a date by which the task must be completed.
- Select Save.
- When you are ready to accept the proposed due date, you can do either of the following:
- In the Task Details dialog box, select Accept.
- Right-click a basic or configurable task card, and then select Accept Proposed Due Date.
- All changes made to this page are saved automatically.
Tips
- If configurable task cards are enabled, you can add a proposed due date directly on the card.
- The Proposed Due Date icon on a task card or in the info bar indicates that the task has a proposed due date that has not been accepted.
- Overdue tasks display a calendar with a status icon to indicate that they need to be adjusted.
- An activity band containing a planned task that exists outside its activity start date or after its end date will display a calendar with a status icon and have a dashed border. This band will also extend farther than other activity bands on the planning board.
- You cannot propose a due date on completed tasks.
- If a task is part of a hand-off chain, changing its due date directly, accepting a proposed due date, or setting a new committed due date will cause the task and other tasks in the chain to be moved. The current hand-off mode determines the movement of a hand-off chain when any of the tasks in the chain are modified:
- Keep Hand-offs: Maintain hand-off logic, but allow for the addition or consumption of slack between tasks.
- Break Hand-offs: Only maintain hand-off logic until the slack between two tasks reaches zero.
Last Published Wednesday, October 16, 2024