Add Hours to an Activity for a Resource
Timesheet supervisors can enter hours against an activity for a project on behalf of a resource assigned to a project that they supervise. You can select any activity from a project that the user has access to even if the user is not assigned as a resource on that activity.
To enter hours for a resource:
- In the header, select your username.
- On the User menu, select Timesheets.
- On the Timesheets page, select Supervisor's Timesheets from the View menu on the toolbar.
- Select a timesheet from the Name column.
- On the Timesheet Details page, select a resource beneath a project, select the Context menu, and then select Add Hours.
- In the new row, select an activity.
- (Optional) Add a Project Supervisor if a default supervisor has not been added for the project.
- (Optional) In the Hour Type column, select the type of hours for which you are logging time, such as overtime, holiday time.
- Enter hours for each day in the time period.
- Select Save.