Import Activities from Microsoft Excel
You can import activities and activity data into the application from a Microsoft Excel (.xls or .xlsx) file. After downloading the import template, follow the instructions to create or update activities in the spreadsheet. The import will fail if there are any invalid values in the spreadsheet. You can download the spreadsheet file to view and fix the errors indicated in the error column at the end of each worksheet, and then import the file again.
You must have sufficient privileges to perform this task.
To import activities from Microsoft Excel:
- Navigate to the project Activities page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Schedule, and then select Activities.
- On the Activities page, select the Actions menu, and then select Import.
- In the Import Activities dialog box, select Browse, select a file, and select Import.
Tips
- Import functionality is only available for the current schedule.
- The Owner field will be empty when an activity is created, even if the activity had an assigned owner prior to being imported. A user must be manually added to the Owner field for a team member to begin tracking an activity. See Assign an Owner to an Activity.