View Tasks Analysis Metrics

Use the Analysis page to view various task performance metrics. Filter task data by the current week, over a six-week time period, or over a custom date range. Use quick filters to limit the analysis results to the companies you choose.

To view Tasks analysis metrics:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Tasks, and then select Analysis.
  3. In the Time Frame list, select one of the following:
    • This Week: Displays the current week's task metric data.
    • 6 Week Window: Displays task metric data for the previous four weeks, the current week, and the next week.
    • Custom: Displays weekly task metric data for a user-defined date range:
      • From: Select a start date for the custom time period.
      • To: Select an end date for the custom time period.
  4. In the Quick Filters list, select the companies you want to include in the analysis results.
  5. Hover over individual bars for additional chart details.

Tips