Assign a Fund to Actuals

You can assign funds to your actuals to track sources of money paid for work rendered. Assigning funds to actuals enables you to track where funds are consumed.

Any changes made to a fund assignment in an actual is reflected in the fund itself. For example, if you assign $50.00 of a fund to an actual, then the fund itself will show that $50.00 has been consumed.

To assign a fund to an actual:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Cost and Funds, and then select Actuals.
  3. On the Actuals page, in the table, select an actual.
  4. Select the Funds detail window, and then select Add.
  5. In the new row, complete these fields:
    • Fund Name: Select a fund.
    • Assigned: Enter the amount to assign to the actual.
  6. Add any additional funds.
  7. (Optional) Select the Actions menu, and select Distribute Evenly Across Funds to distribute the Assigned amount evenly across the funds listed.
  8. Select Save.

Tips

Related Video Tips

Distribute a Fund Evenly Video