Assign Probability and Impact Values to a Risk

Video

The probability, schedule impact, and cost impact values entered for each risk are used to calculate the risk score. Choose from a selection of threshold values determined by the assigned risk matrix. Use the risk register to define risk values for pre-response and post-response contexts.

To assign probability and impact values to a risk:

  1. In the object selector, select Project or Program, and then select a project or a program from the list.
  2. From the Main Menu, select Risk, and then select Risk Register.
  3. In the table, select a risk with a Type of Threat or Opportunity.
  4. In the Pre-Response Probability column, select a probability threshold.
  5. In the Pre-Response Schedule column, select a schedule threshold.
  6. In the Pre-Response Cost column, select a cost threshold.

    Note: Add Post-Response Probability, Post-Response Schedule, and Post-Response Cost columns to assign post-response values to risks.

  7. Select Save.

Tips