View Risk Mean Impact Analysis Results
View the average impacts of activities and risks on the project cost and finish date.
To view risk mean impact analysis results:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Risk, and then select Risk Analysis.
- Select the Mean Impact tab.
- In the Response Context list, select an analysis context:
- Pre-Response: Displays analysis results based on pre-response values.
- Post-Response: Displays analysis results based on post-response values.
- In the Show list, view analysis results for Activity Delay Contribution, Activity Cost Contribution, Risk Delay Contribution, and Risk Cost Contribution.
Note: Available activity results are determined by your risk analysis settings.
- To filter the number of results, select Settings and configure the display options.
- Select Show Contribution Breakdown for:
- Activity Delay Contribution and Activity Cost Contribution to display the impact breakdown by risk.
- Risk Cost Contribution to display the breakdown by direct cost impact and schedule cost impact.
Tips
- You can see the start date, end date, and duration of the most recently run risk analysis in the Risk Analysis Run Settings.
- You can configure the date format to include time to see the exact start and end time of the risk analysis. See Configure the Date Format for more information.